2026 Stormwater Facility Inspections

Inspections Due in 2026

2006 Agreements

All facilities with agreements from 2006 are required to have their inspections in 2026. These reports are due by August 13, 2026.

2011 Permits

All facilities with permits from 2011 are required to have their inspections in 2026. These reports are due by August 15, 2026.

  • Quail Haven Subdivision: 1 wet pond
  • Quail Haven Addition Number 1 Subdivision: 1 wet pond
  • CVS:
    • 2010-05 Permit (PDF)
    • Map (PDF)
    • 2026 Report - SWP11S001 (PDF): 1 bio-filter
    • 2026 Report - SWP11S002 (PDF): 1 bio-filter
    • 2026 Report - SWP11S003 (PDF): 1 stormceptor
    • 2026 Report - SWP11S004 (PDF): 1 stormceptor
    • 2026 Report - SWP11S005-010 (PDF): 6 underground storage tanks
    • 2026 Report - SWP11S011 (PDF): 1 bio-filter
  • We Energies CP-26: 1 wet pond, 1 underground detention
  • Brook-Falls Veterinarian: 1 wet pond
  • Breezy Hill Nursery: 1 wet pond, 1 wet Fore bay pond, 1 infiltration pond
  • Willow Springs School: 1 dry pond
  • Weyer Road Soccer Fields: 1 wet pond
  • Wacker: 1 dry pond
  • Menomonee Falls Elderly Assisted Living Facility: 
  • Menomonee Falls Elderly Assisted Living Facility: 
    • 2011-03 Permit (PDF) 
    • Map
    • 2026 Report - SWP09S005 (PDF): 1 bio-filter pond
    • 2026 Report - SWP09S006 (PDF): 1 bio-filter pond
    • 2026 Report - SWP09S007 (PDF): 1 bio-filter pond
    • 2026 Report - SWP09S008 (PDF): 1 bio-filter pond
    • 2026 Report - SWP09S012 (PDF): 1 underground storage
    • Map-Phase 1 (PDF): 4 bio-filter ponds built and 1 underground storage were built in Phase 1
    • Map-Phase 2 (PDF): 3 bio-filter ponds and 1 underground storage will be built in Phase 2
  • Eaton: 2 wet ponds

2016 Permits

All facilities with permits from 2016 are required to have their inspections in 2026. These reports are due by August 13, 2026.

  • Christman Park Subdivision: 1 wet pond
  • Community Memorial Hospital
    • 2016 Permit
    • Map
    • 2026 Report - SWP09S002 (PDF)
  • Keystone Riverview Condos
  • Riverwalk on the Falls
  • Fox Meadows
    • 2016-03 Permit (PDF)
    • Map
    • 2026 Report - SWP22S002 (PDF): 1 dry pond
    • 2026 Report - SWP22S003 (PDF): 1 wet pond 
    • 2026 Report - SWP22S004 (PDF): 1 wet pond 
    • 2026 Report - SWP22S005 (PDF): 1 dry pond 
    • 2026 Report - SWP22S006 (PDF): 1 wet pond 
    • 2026 Report - SWP22S007 (PDF): 1 dry pond 
    • 2026 Report - SWP22S008 (PDF): 1 wet pond 
    • 2026 Report - SWP22S009 (PDF): 1 wet pond
  • ER Wagner
  • Home2 Suites - Transfer from VMF
  • Zilber Parking Lot Lilly Road
  • Fairchild Equipment
  • Shady Lane School

2021 Permits

All facilities with permits from 2021 are required to have their inspections in 2026. These reports are due by August 15, 2026.

  • Grace Commons/Capri: 3 wet ponds
  • Ascension: 1 wet pond
  • Sanctuary at Good Hope: 2 dry pond / 3 wet ponds / 2 rain gardens
    • 2020-05 Permit (PDF)
    • Map
    • 2026 Report SWP21N001 (PDF): 1 dry pond
    • 2026 Report SWP21N002 (PDF): 1 dry pond
    • 2026 Report SWP21N003 (PDF): 1 wet pond 
    • 2026 Report SWP21N004(PDF): 1 wet pond 
    • 2026 Report SWP21N005 (PDF): 1 wet pond 
    • 2026 Report SWP21N006 (PDF): 1 rain garden
    • 2026 Report SWP21N007 (PDF): 1 rain garden
    • 2026 Report SWP21N008 (PDF): 1 rain garden
  • Pilgrim Landing Apartments: 1 wet pond
    • 2020-08 Permit (PDF)
    • Map
    • 2026 Report - SWP22N003 (PDF)
  • Chick-Fil-A: 1 underground system
  • RJ Schinner: 1 dry pond and 1 dry pond w/bio-filter
  • Evergreen Fields Subdivision: 2 wet ponds
  • Sommersfield Subdivision: 2 wet ponds
  • Edgewood Preserve: 2 wet ponds
    • 2021-05 Permit (PDF)
    • Map
    • 2026 Report - SWP16S007 (PDF)
    • 2026 Report - SWP16S008 (PDF)
  • Redline (Milwaukee Tool): 1 underground system

Biannual Inspections

Biannual Inspections due May 15 and November 15, 2026.

  • Pilgrim Spring Market Place: porous pavement
  • ALPS Pharmacy: porous pavement 
    • 2020-01 Green Infrastructure Permit (PDF) 
    • Map
    • 2026 May Report - SWP36S008 (PDF)
    • 2026 November Report - SWP36S008 (PDF)

Village Inspections on Stormwater Facilities

Due:

  • Megal Ct: 1 wet pond
    • Map
    • 2026 Report - SWP02N016 (PDF)
  • TID #8 - Phase I: SW Corner Pilgrim Rd & Falls Pkwy: 1 wet pond
    • Map
    • 2026 Report - SWP03S003 (PDF)
  • Mill Pond Parking Lot S of Roosevelt Rd: 
    • Map
    • 2026 Report - SWP03S009 (PDF): 1 bio-swale
    • 2026 Report - SWP03S010 (PDF): 1 rain garden 
  • Village Park Amphitheater: 1 dry pond
    • Map
    • 2026 Report - SWP10N001 (PDF)
  • Combined Public Works Facility: 2 wet ponds
    • Map
    • 2026 Report - SWP15S004 (PDF)
    • 2026 Report - SWP15S005 (PDF)
  • Willowood Park: 1 wet pond
    • Map
    • 2026 Report - SWP35N006 (PDF)