2021 Stormwater Facility Inspections

Inspections Due



All facilities with agreements from 2006 are required to have their inspections in 2021. These reports are due by August 13, 2021.  


    
  • Harmony Hills II Subdivision: 4 wet ponds and 1 dry
  • Lilly Creek Highlands IV Subdivision: 3 wet ponds and 1 dry pond 
  • Little League Expansion: 5 dry ponds with filter material
  • Pizzeria Uno on Premier Lane: 1 dry pond with filter material
  • Reich Tool & Design/AJ Die-Namics: 1 wet pond and 1 dry pond
  • Spencer’s Pass East Subdivision: 1 wet pond
  • Super Excavators: 1 underground system
  • Wildwood Lake: 1 wet pond
 

All facilities with permits from 2011 are required to have their inspections in 2021. These reports are due by August 13, 2021.
  

  • We Energies CP-26:  1 wet pond, 1 underground detention
  • Wacker: 1 dry pond
  • Breezy Hill Nursery:  1 wet pond, 1 wet Fore bay pond, 1 infiltration pond
  • Menomonee Falls Elderly Assisted Living Facility:  4 bio-filter ponds built and 1 underground storage,                              and 3 bio-filter ponds and 1 underground storage will be built in phase 2
  • CVS: 6 underground storage tanks, 2 stormceptors, 2 sand filters, 1 bio-filter pond, 1 dry temporary pond
  • Eaton: 2 wet ponds
  • Willow Springs School:  1 dry pond
  • Weyer Road Soccer Fields: 1 wet pond
  • Quail Haven Subdivision: 1 wet pond
  • Quail Haven Addition #1 Subdivision:  1 wet pond
  • Brook-Falls Veterinarian:  1 wet pond
 All facilities with permits from 2016 are required to have their inspections in 2021.  These reports are due by August 13, 2021.
  • Community Memorial Hospital
    • 2016 Permit and map      2021 Report 
  • ER Wagner
  • Keystone Riverview Condos
  • Riverwalk on the Falls
  • Fox Meadows
    • 2016 Permit and map      2021 Report 
  • Aquinas Academy
  • Tamarind Subdivision
    • 2016 Permit and map      2021 Report 
  • Home2 Suites
  • Fairchild Equipment
  • Shady Lane School
  • Zilber Parking Lot Lilly Road


Biannual Inspections due May 15 and November 15, 2021 
           
           Pilgrim Spring Market Place: Porous Pavement
   2015 Permit    May Report    November Report

Village Inspections on Stormwater Facilities are due:
  
  • SWP15s004 Good Hope Garage:  1 wet pond
  • SWP3s003 TID 8 pond Pilgrim Rd and Falls Parkway: 1 wet pond

As-Builts Submitted
 2021 As-builts